LAS VEGAS, Jan. 08, 2025 (GLOBE NEWSWIRE) -- Asia Broadband Inc. (OTC: AABB) ("AABB” or the "Company”) is pleased to announce the following corporate update for the Company:
Mining Operations Update
Etzatlan Plant:
Our engineering team is expecting to have the processing plant operating by mid-March 2025. We have encountered many delays with the delivery of equipment from one of our key suppliers in China, specifically Henan Mecru Heavy Industry Co. Ltd. Additionally, severe weather and permitting issues has set our projected start date timeline back over 12 months. However, our on-site assay laboratory is fully functional and has been operating for many months now. Numerous samples from taken from our Stockpile and nearby concessions have been analyzed with very positive results.
The first line of production, which is a mineral flotation process, will be capable of producing up to 500 tons per day. The initial processing target will be 350 tons per day for the first 3 months and then gradually increase to 500 tons per day. With an average production cost of $56.75 USD per ton, we estimate a net revenue of $1,973,282 USD in the first 3 months of operations and $10,430,207 USD in the first 12 months. Our second line of production, which is a cyanidation process, is also estimated to go into production September 2025, with an initial target of 200 tons per day for the first 4 months and gradually increase to 500 tons per day. Since the cyanidation process produces a higher yield, the estimated net revenue is expected to increase to $2,322,152 USD in the first 4 months of operations and $13,932,912 USD in the first 12 months.
As an industry leader in innovation and breaking away from traditional methodologies, the Company will be installing a series of Live Streaming Video cameras onsite. We believe this a first ever live stream from any mineral processing plant, giving real time access to our investors.
Also in Q2 2025, the Company expects to have guided investor tours of our processing plant.
Stockpile Agreement (Las Jimenez):
To date, 8,000 tons of strategically targeted ore has been delivered onsite to our plant in Etzatlan. Another 10,000 tons is expected to be delivered before we begin operations in March 2025. This supply will serve as a building block to start our first line of production. In January 2025, a new Qualified Person (QP) Geologist has been hired to perform additional Sonic drilling programs on the current Stockpile and on an additional estimated 2,000,000 tons of tailings dump nearby, which the Company is in negotiations to acquire from the landowners. We expect to have a complete NI 43-101 geological report certified by new QP by end of February. The report is expected to further validate the value of our Stockpile Agreement and attract a larger investor base.
Bonanza (concession #221977, 19.25 hectare):
The Company received its second Geological report NI 43-101 from MICON. After careful evaluation by our geological team, the Company has decided it would be more beneficial to focus all efforts on assets and mining concessions located nearby our Etzatlan plant. Therefore, the Company is currently in negotiations with two potential buyers and has also received a purchase offer from another buyer for the amount of $8,000,000 USD that was declined.
Tequila Joint Venture (concession #219165, 66.6792 hectare):
Record production has increased in the Tequila Joint Venture in 2024, which has been attributed to higher-grade recoveries, increased daily throughput levels and reduced production costs from economies of scale. The Company estimates the same production level will continue over the next year and will be focusing efforts on higher grade recoveries and possibly processing in our Etzatlan plant to obtain higher yields.
Picachos IV (concession #239735, 4,081 hectare):
The mining concession has now been registered with the Mexican mining registry. The Company is continuing to progress with its Phase 1 drill exploration program in the prolific mining region.
La Paz (concession #236301, 184 hectare):
Phase II drilling program continues with a total of 2,200 meters drilled to date. In addition, a 200-meter-deep old mining shaft has been discovered on the property. Further exploration of this mining shaft in ongoing.
Zodiac I
Haftungsausschluss:info@kdj.com
Die bereitgestellten Informationen stellen keine Handelsberatung dar. kdj.com übernimmt keine Verantwortung für Investitionen, die auf der Grundlage der in diesem Artikel bereitgestellten Informationen getätigt werden. Kryptowährungen sind sehr volatil und es wird dringend empfohlen, nach gründlicher Recherche mit Vorsicht zu investieren!
Wenn Sie glauben, dass der auf dieser Website verwendete Inhalt Ihr Urheberrecht verletzt, kontaktieren Sie uns bitte umgehend (info@kdj.com) und wir werden ihn umgehend löschen.
-
- Strategy kauft Bitcoin: Saylor meldet riesige Bitcoin-Vermögenswerte, MicroStrategy-Bitcoin-Bestände steigen auf 845.050 BTC
- Sep 01, 2026 at 04:05 am
- Strategy hat seinen Bitcoin-Schatzbestand erweitert und 4.603 BTC im Wert von 370 Millionen US-Dollar erworben, wodurch sich der Gesamtbestand auf 845.050 BTC erhöht, während gleichzeitig erhebliche USD-Vermögenswerte und ein Netto-Leverage von Null beibehalten wurden.
-
- Islands EU-Ablehnung legt MiCA-Anpassung auf Eis, Abstimmungsverzögerungen werden erwartet
- Aug 31, 2026 at 04:05 pm
- Islands jüngstes Referendum über den EU-Beitritt hat erhebliche Auswirkungen auf die Kryptoindustrie, da es die vollständige Angleichung an das MiCA verzögert und neue Regulierungslandschaften schafft.
-
- Cronos-Netzwerk wegen 75-Millionen-Dollar-Exploit gestoppt: Das Tectonic-Protokoll erleidet einen schweren Schlag
- Aug 31, 2026 at 04:05 pm
- Die Cronos-Blockchain wurde nach einem 75-Millionen-Dollar-Exploit auf Tectonic, einem wichtigen Kreditprotokoll, aufgrund eines Preismanipulationsangriffs gestoppt. Ermittlungen laufen.
-
- LUNCs Billionen-Token-Genesis: Das Münzereignis im Mai 2022 und der lange Weg, der vor uns liegt
- Aug 31, 2026 at 04:05 pm
- Im Mai 2022 explodierte das Angebot von LUNC innerhalb einer Woche von 400 Millionen auf 6,5 Billionen. Jetzt bekämpft die Gemeinschaft dieses riesige Angebot mit einer Verbrennungssteuer von 1,5 % und Umtauschbeiträgen, aber eine deutliche Preiswirkung bleibt ein fernes Ziel.
-
- Hervorragende RWA-Wertsteigerungen, die reale Vermögenswerte in einer New Yorker Minute neu definieren
- Aug 31, 2026 at 04:05 pm
- Die tokenisierten realen Vermögenswerte (RWAs) von Stellar sind um 360 % auf fast 4 Milliarden US-Dollar im Jahr 2026 gestiegen, was einen großen institutionellen Wandel hin zu Blockchain-basierten Finanzen signalisiert und einen dynamischen, sich schnell entwickelnden Markt darstellt.
-
- Sberbank nutzt Ethereum und USDT für kryptogestützte Kredite und bewältigt neue russische Vorschriften
- Aug 31, 2026 at 04:05 pm
- Die Sberbank erweitert ihre Krypto-Kreditvergabe um Ethereum und USDT und passt sich damit dem neuen digitalen Währungsrahmen Russlands an, der am 1. September in Kraft treten soll.
-
-
- Die August-Rallye von Bitcoin stößt auf Gegenwind: Wichtige Krypto-Signale tauchen inmitten der sich verändernden Marktdynamik auf
- Aug 31, 2026 at 04:05 pm
- Die starke Bitcoin-Rallye im August zeigt Anzeichen einer Verlangsamung. Untersuchung steigender Devisenreserven, ETF-Abflüsse und Spotmarktsignale für Krypto-Einblicke.
-